Sandall Park Design
£95,053
value
GBP
10 Feb 2025
awarded
1
suppliers named
Who
| Buyer | Doncaster |
| Supplier | Alan Wood & Partners |
What
Alan Wood & Partners to undertake the vertical & horizontal alignment design as well as drainage for the Doncaster East Project for the section between Shaw Lane Roundabout to Sandall Park Roundabout, to meet the CRSTS funding programme which aims to deliver transformational change through investments in public and sustainable transport infrastructure. This was procured via a framework agreement.
Dates and source
| Runs | 17 Feb 2025 to 31 Jul 2025 |
| OCID | ocds-b5fd17-bdbfd1cb-65dc-47ef-9b9b-a6fbdd17f2d2 |
| Notice | Read it on Contracts Finder |
Figures are as published An award value in OCDS may be a framework ceiling rather than a sum anyone expects to spend, so a large figure here is not evidence of a large purchase.