UKRI-3039 BGS Ground Source Heat Pump Heating System to Serve James Hutton Building and SRMR
£2,800,000
value
GBP
2 Jan 2024
awarded
1
suppliers named
Who
| Buyer | UK Research & Innovation — not a council we hold |
| Supplier | Cenergist Limited |
What
The British Geological Survey require a contractor for delivery of the next phase of decarbonisation at the Head Office site in Keyworth, Nottingham. The works are expected to involve design, procurement, installation and commissioning of a ground a source heating system to serve the James Hutton and SRMR Buildings and associated adaptions to accommodate this works including BMS upgrades.
Dates and source
| Runs | 8 Jan 2024 to 31 May 2024 |
| OCID | ocds-b5fd17-69d54c3e-bf3f-41c1-b135-4fd969206878 |
| Notice | Read it on Contracts Finder |
Figures are as published An award value in OCDS may be a framework ceiling rather than a sum anyone expects to spend, so a large figure here is not evidence of a large purchase.