GCP CEA Newmarket Road phase 2 detailed design
£324,216
value
GBP
18 Dec 2023
awarded
1
suppliers named
Who
| Buyer | Cambridgeshire |
| Supplier | WSP Ltd |
What
Detailed design of Phase 2 Section 1 Cambridge Eastern Access (CEA). Phase 2 of the CEA Newmarket Road scheme is approximately 1.3km in length, between the Meadowlands Road and Airport Way junctions
Dates and source
| Runs | 1 Feb 2024 to 1 Sep 2024 |
| OCID | ocds-b5fd17-72ce8d19-8ce4-42f5-afbf-8cf1831b0143 |
| Notice | Read it on Contracts Finder |
Figures are as published An award value in OCDS may be a framework ceiling rather than a sum anyone expects to spend, so a large figure here is not evidence of a large purchase.