GMCA 1115 Consultancy to Support the Old Trafford Regeneration Project Phase 0-1
Who
| Buyer | Greater Manchester Combined Authority — not a council we hold |
| Supplier | Deloitte LLP |
What
Consultancy to Support the Old Trafford Regeneration Project Phase 0-1\r \r The scope for the Lead Advisory team over the initial 2 months includes the following activities:\r \r Stage 0 (1 month) - Project review and programme plan development\r \r Detailed review and assessment of current state in order to develop a detailed programme plan for the next phases of work. This will require consideration of the current position with regard to the key workstreams identified below, and the overall project geography and timetable.\r \r The output will be a detailed programme of work for stages 1 and 2, a project plan with key milestones, detailed for stages 1 and 2 and indicative beyond this to project completion, and a cost plan.
Dates and source
| Runs | 27 Aug 2024 to 30 Nov 2024 |
| OCID | ocds-b5fd17-6c7f003f-905f-4f8d-827f-e9179e5ac855 |
| Notice | Read it on Contracts Finder |
Figures are as published An award value in OCDS may be a framework ceiling rather than a sum anyone expects to spend, so a large figure here is not evidence of a large purchase.