Preparation and submission of a S.73 planning application to amend the landscape design and the commencement date of the existing planning permission. Carrying out refreshed ecological surveys due to the expiry of information collected previously before construction commences. These are to comprise of ecological site walkover, aquatic ecology survey, riparian mammal survey along with reports for each. Also included is an arboriculturally method statement.
Dates and source
| Runs | 2 Nov 2024 to 1 Nov 2026 |
| OCID | ocds-b5fd17-7c80bfd5-1e84-47e6-86da-6ea4a22d4864 |
| Notice | Read it on Contracts Finder |
Figures are as published An award value in OCDS may be a framework ceiling rather than a sum anyone expects to spend, so a large figure here is not evidence of a large purchase.