Decision - Moulsecoomb Hub and Housing Project
As published
the council's own words, uneditedAn update on the Moulsecoomb project seeking approval for a way forward
RESOLVED: That Housing and New Homes Committee recommends to Strategy, Finance and City Regeneration Committee to: 2.1 Agree to begin a procurement exercise for the redevelopment of this site, including early market engagement. 2.2 Delegate authority to the Executive Director of Environment, Economy & Culture and the Executive Director Housing, Neighbourhoods & Communities to procure the contractors and then once a budget has been agreed at a subsequent committee meeting, to then enter in to relevant contracts. 2.3 Note that the demolition of some of the existing buildings is due to commence in March 2024.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 5411/1323 tokens · 12696ms · parsed 9 Sep 2026 15:26The report proposed progressing the Moulsecoomb Hub and Housing project through a competitive Design and Build procurement process rather than the existing Strategic Partnership. The scheme is intended to deliver more than 200 affordable homes, a community hub and improved public spaces, with demolition of some existing buildings planned to begin in March 2024.
Stakeholders named
parsedNext steps
parsed- Begin contractor market engagement in March 2024.
- Issue the selection questionnaire in May 2024 and shortlist suitable suppliers.
- Issue the Invitation to Tender in July 2024 and evaluate tenders in September 2024.
- Bring a further report to committee seeking full budget approval once costs and any Section 73 planning requirements are known.
- Award the contract, subject to budget approval, in November 2024, with an anticipated start on site in January 2025.
- Commence demolition of some existing buildings in spring 2024 for approximately 15 weeks.