Decision - The King Alfred Leisure Centre Regeneration Project - Progress Update
As published
the council's own words, uneditedThis report is an update on progress in delivering the King Alfred Regeneration Project. It includes recommendation to draw down further funding from the agreed budget in order to complete enabling works ahead of main construction, scheduled to begin in November 2026
That Cabinet: 1) Agrees that the Council enters into Development Management Agreements with Alliance Leisure for enabling works on the new King Alfred leisure facility site including the demolition of the disused bowling alley area. 2) Agrees to delegate authority to the Corporate Director City Operations in consultation with the cabinet member for Sports, Recreation and Libraries to finalise the terms of the Development Management Agreements and enter into the Development Management Agreement and any ancillary documentation. 3) Agrees to bring forward the allocation of £3.5m from previously agreed project capital budget to fund these works up to November 2026.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 10535/3167 tokens · 20565ms · parsed 8 Sep 2026 11:34Cabinet was asked to approve the next stage of the King Alfred Leisure Centre regeneration project. The proposal was to enter into agreements with Alliance Leisure Services and allow Willmott Dixon Construction to undertake enabling works, including demolition of the disused bowling alley, funded by bringing forward £3.5 million from the existing capital budget.
Stakeholders named
parsedNext steps
parsed- Finalise and enter into Development Management Agreements with Alliance Leisure.
- Commence enabling works, scheduled for May 2026, including the temporary car park, site compound, service diversions and demolition of the disused bowling alley.
- Submit the final Ecological Mitigation Strategy in April 2026 and obtain formal discharge before demolition starts in July 2026.
- Continue the planning process for application BH2026/00490.
- Bring a further report to Cabinet in September or October 2026 seeking approval of the final budget and the main construction delivery agreement.
- Subject to planning and further Cabinet approval, begin construction of the new facility in November 2026.