Decision - Planned Maintenance Budget and Asset Management Fund Allocations and Education Capital Resources and Capital Investment Programme 2026-2027

Brighton and Hove Cabinet Decided 19 Mar 2026 · effective 28 Mar 2026 approved Key decision GET /api/coverage
Decision maker
Cabinet
Report author
Yann Vochelle
Published
20 Mar 2026
Reference
7596

As published

the council's own words, unedited

This Report requests Cabinet to - note the level of available capital resources totalling £3,305,000 for investment relating to education buildings for 2026-27. - agree to the allocation of funding for inclusion within the Council's Capital Investment Programme 2026-27. - approve the annual programme of planned maintenance works within the Planned Maintenance Budget for 2026-27, at a total estimated cost of £4,309,540. - approve the allocations from the Asset Management Fund for 2026-27, at a total estimated cost of £1,000,000. - delegate authority to the Director of Property & Finance to take all steps necessary to procure the capital maintenance and basic needs works, Planned Maintenance Budget works and Asset Management Fund improvement works, and award contracts within these budgets and in accordance with Contract Standing Orders.

1) Cabinet notes the level of available capital resources totalling £5,569,000m for investment relating to education buildings. 2) Cabinet agrees the allocation of funding as shown in Appendix 1 for inclusion within the council's Capital Investment Programme 2026/27. 3) Cabinet grants delegated authority to the Director of Property & Finance to procure the capital maintenance and basic need works required, as set out in Appendix 1, and enter into contracts in accordance with Contract Standing Orders. 4) Cabinet approves the annual programme of planned maintenance works within the Planned Maintenance Budget for 2026/27 as detailed in Appendix 2, at a total estimated cost of £4,509,540. 5) Cabinet approves the allocations from the Asset Management Fund for 2026/27, totalling £1,000,000, as detailed in Appendix 3. 6) Cabinet delegates authority to the Director of Property & Finance to take all steps necessary to procure the Planned Maintenance Budget works and Asset Management Fund improvement works and award contracts within these budgets and in accordance with Contract Standing Orders.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 4926/2406 tokens · 18186ms · parsed 8 Sep 2026 11:36
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The document identifies urgent and essential planned maintenance works across council buildings, venues, seafront assets, sports facilities and other sites to support funding bids for 2026/2027. The estimated total cost of the listed works and maintenance contributions is £4,009,540.00.

Recommendation
Submit the identified condition survey data and estimated maintenance costs to support planned maintenance budget funding bids for 2026/2027, prioritising works rated urgent.
Financial impact
Estimated total planned maintenance requirement of £4,009,540.00, including £308,958.00 for Brighton Dome, £564,000.00 for Royal Pavilion and other Museums, £943,286.32 for term contracts, £575,000.00 for Brighton Centre, £280,000.00 for 9-11 Rutland Gardens, £109,788.65 for Hollingdean Depot, £150,000.00 for seafront works, £79,000.00 for Volk's Railway, £642,000.00 for sports and leisure works and £357,507.03 for various sites.
Ward affected
city-wide

Stakeholders named

parsed
Brighton DomeRoyal Pavilion and other MuseumsBrighton CentreHove Town Hall9-11 Rutland GardensHollingdean Depot - Workshop BuildingSeafront PromenadePeter Pan playground (Madeira Drive)Volk's RailwayThe ManorPrince Regent Swimming Complex

Next steps

parsed
  • Complete and email the condition survey data to amp@brighton-hove.gov.uk.
  • Submit the information no later than 2025-12-31.
  • Use the identified urgent works to support planned maintenance budget funding bids for 2026/2027.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage