Decision - Brighton Marina to River Adur Flood and Coastal Erosion Risk Management (FCERM) scheme – Project Update and Phase Two Procurement Strategy

Brighton and Hove Cabinet Decided 24 Apr 2025 · effective 3 May 2025 approved Key decision GET /api/coverage
Decision maker
Cabinet
Report author
Steven Parker
Published
25 Apr 2025
Reference
7439

As published

the council's own words, unedited

This report seeks to revise the delegated authority given to the Interim Corporate Director City Operations to procure and award a construction contract for the accelerated construction elements of the FCERM scheme.

1) Cabinet agrees to increase the capital contribution for the BHCC Phase 2 works from £6.515m to £11m for the Brighton Marina to River Adur Flood and Coastal Erosion Risk Management (FCERM) Scheme. 2) Cabinet agrees to release the unapproved sums - allocated to the Scheme for the purposes of BHCC Phase 2 works and contained within the forward capital plan - to approved status . These sums are stated in Part 2 3) Cabinet agrees to authorise an open procurement process to select a suitable and competent supplier to carry out the BHCC Phase 2 construction works within the BHCC area. 4) Cabinet delegates authority to the Corporate Director City Operations to take all steps necessary to award a suitable construction contract to the preferred bidder and enter into the contract and any associated warranties / documents. 5) Cabinet delegates authority to the Corporate Director City Operations to take all steps necessary to act as Lead Authority in project managing the Scheme on behalf of the stakeholders and the Environment Agency. This includes providing a loan to Shoreham Port Authority for the value of the works within their area of circa £2.5m. This forms part of the overall budget of £11m as stated in 2.1 above.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 5685/1533 tokens · 11865ms · parsed 9 Sep 2026 15:34
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

Cabinet approved an increase in Brighton & Hove City Council’s capital contribution to Phase 2 of the Brighton Marina to River Adur flood and coastal erosion scheme from £6.515 million to £11 million. It also approved releasing the allocated budget, starting an open procurement process for the construction works, and delegated authority to award the contract and manage the scheme, including a proposed £2.5 million loan to Shoreham Port Authority.

Outcome
approved
Recommendation
Approve the increased £11 million capital contribution for Brighton & Hove City Council’s Phase 2 works; release the unapproved budget sums; authorise an open procurement process; delegate authority to award and enter into the construction contract; and delegate authority to act as Lead Authority and provide a loan of approximately £2.5 million to Shoreham Port Authority.
Financial impact
Brighton & Hove City Council’s Phase 2 capital contribution increases from £6.515 million to £11 million. The overall scheme value has increased from £35.526 million to £41.5 million, with an approved grant contribution of £14.085 million and anticipated further grant funding of £5.414 million.
Ward affected
city-wide
Decision maker
Cabinet
Date in document
24 Apr 2025

Stakeholders named

parsed
Brighton & Hove City CouncilAdur & Worthing CouncilsShoreham Port AuthorityEnvironment Agencyresidentsbusiness ownerseducational facilitiesseafront businessesschools

Next steps

parsed
  • Release the unapproved sums allocated to the scheme into approved budget status.
  • Complete and issue the Phase 2 tender package through the In-Tend portal by the end of April 2025.
  • Run an open procurement process and award the construction contract under delegated authority.
  • Agree and complete the loan arrangements with Shoreham Port Authority, subject to due diligence and subsidy-control requirements.
  • Begin Kings Esplanade works around September 2025, with completion around May 2026.
  • Begin Southwick Beach works during 2026, with completion by April 2027.
  • Submit the revised Outline Business Case and request for additional funding to the Environment Agency.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.