Decision - Brighton Marina to River Adur Flood and Coastal Erosion Risk Management (FCERM) scheme – Project Update and Phase Two Procurement Strategy
As published
the council's own words, uneditedThis report seeks to revise the delegated authority given to the Interim Corporate Director City Operations to procure and award a construction contract for the accelerated construction elements of the FCERM scheme.
1) Cabinet agrees to increase the capital contribution for the BHCC Phase 2 works from £6.515m to £11m for the Brighton Marina to River Adur Flood and Coastal Erosion Risk Management (FCERM) Scheme. 2) Cabinet agrees to release the unapproved sums - allocated to the Scheme for the purposes of BHCC Phase 2 works and contained within the forward capital plan - to approved status . These sums are stated in Part 2 3) Cabinet agrees to authorise an open procurement process to select a suitable and competent supplier to carry out the BHCC Phase 2 construction works within the BHCC area. 4) Cabinet delegates authority to the Corporate Director City Operations to take all steps necessary to award a suitable construction contract to the preferred bidder and enter into the contract and any associated warranties / documents. 5) Cabinet delegates authority to the Corporate Director City Operations to take all steps necessary to act as Lead Authority in project managing the Scheme on behalf of the stakeholders and the Environment Agency. This includes providing a loan to Shoreham Port Authority for the value of the works within their area of circa £2.5m. This forms part of the overall budget of £11m as stated in 2.1 above.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 5685/1533 tokens · 11865ms · parsed 9 Sep 2026 15:34Cabinet approved an increase in Brighton & Hove City Council’s capital contribution to Phase 2 of the Brighton Marina to River Adur flood and coastal erosion scheme from £6.515 million to £11 million. It also approved releasing the allocated budget, starting an open procurement process for the construction works, and delegated authority to award the contract and manage the scheme, including a proposed £2.5 million loan to Shoreham Port Authority.
Stakeholders named
parsedNext steps
parsed- Release the unapproved sums allocated to the scheme into approved budget status.
- Complete and issue the Phase 2 tender package through the In-Tend portal by the end of April 2025.
- Run an open procurement process and award the construction contract under delegated authority.
- Agree and complete the loan arrangements with Shoreham Port Authority, subject to due diligence and subsidy-control requirements.
- Begin Kings Esplanade works around September 2025, with completion around May 2026.
- Begin Southwick Beach works during 2026, with completion by April 2027.
- Submit the revised Outline Business Case and request for additional funding to the Environment Agency.