Decision - Education Capital Resources and Capital Investment Programme 2022/2023

Brighton and Hove Policy & Resources Committee Decided 24 Mar 2022 GET /api/coverage
Decision maker
Policy & Resources Committee
Report author
Richard Barker
Published
24 Mar 2022
Reference
6577

As published

the council's own words, unedited

1.2 The purpose of the report is to inform the Committee of the level of available capital resources allocated to support education buildings and to recommend a capital programme for 2022/23 in respect of School Condition Allocation (SCA) and Basic Need funding.

RESOLVED : That the Committee granted delegated authority to the Assistant Director of Property & Design to procure the capital maintenance and basic need works and enter into contracts within these budgets, as required, in accordance with Contract Standing Orders in respect of the entire Education Capital Programme.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 2881/3088 tokens · 16711ms · parsed 9 Sep 2026 11:42
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The appendix lists priority condition works across schools, covering asbestos removal, building, roofing, mechanical, electrical, toilet and resurfacing works. The programme totals £3,952,300 including fees for works completing in 2021/22 and £2,370,500 including fees carried forward to 2022/23.

Recommendation
To approve the listed school condition works and associated expenditure, including works completing in 2021/22 and those carried forward to 2022/23.
Financial impact
£3,952,300 including fees for works completing in 2021/22, plus £2,370,500 including fees carried forward to 2022/23; total £6,322,800 including fees.
Ward affected
city-wide

Stakeholders named

parsed
Brighton & Hove schoolsPupilsSchool staffSchool governing bodiesParents and carers

Next steps

parsed
  • Complete the listed 2021/22 school condition works.
  • Carry forward the identified works to the 2022/23 programme.
  • Apply fees at 10% as shown in the appendix.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage