Decision - Valley Gardens Phase 3 revised scheme with detailed design principles

Brighton and Hove Environment, Transport & Sustainability Committee, Policy & Resources Committee Decided 18 Jan 2022 approved GET /api/coverage
Decision maker
Environment, Transport & Sustainability Committee, Policy & Resources Committee
Report author
Oliver Spratley
Published
19 Jan 2022
Reference
6497

As published

the council's own words, unedited

Revised scheme following further public consultation and stakeholder engagement. The updated plans account for significant change to walking and cycling infrastructure design guidance. In addition to the main report appendices are provided which outline detailed design principles and detail where necessary both the temporary and permanent matters related to the scheme. These technical design and engineering principles are set out so that the procurement of a construction contract can be progressed in the coming months with construction to commence thereafter.

1) Approves the Valley Gardens Phase 3 detailed design as shown in Appendix 1: General Highway Arrangement Plan. 2) N otes that the principles and details outlined in this report will help to inform all final technical matters, with regards to this scheme, in preparation for the procurement of a construction contract by officers in line with the decision made by this committee in February 2019 as outlined in paragraph 7.2 of this report. 3) Authorises that all Traffic Regulation Orders required for Valley Gardens Phase 3 be advertised in accordance with the standard procedure. 4) N otes the increased budget requirement due to significant delay in delivering Phase 3, additional stakeholder infrastructure commitments, and significant increases in construction costs, as set out in in Appendix 2. 5) Recommends to Policy & Resources Committee that it approves capital borrowing of up to £5.0m to address estimated increased scheme costs arising from new Department for Transport design guidance; significant increases in construction costs and risk management; additional infrastructure, including for sustainable transport and events; as shown in Appendix 2.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 12115/6573 tokens · 32253ms · parsed 9 Sep 2026 11:49
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The report records engagement and consultation on the Valley Gardens Phase 3 scheme from 2018 to 2021, including 463 public consultation responses and meetings with transport, accessibility, heritage, business and community stakeholders. Feedback led to changes including segregated cycle tracks, more disabled bays, revised bus arrangements, additional public space and improved pedestrian crossings.

Recommendation
To note the engagement and consultation undertaken and use the feedback and design responses to inform the final General Highway Arrangement scheme for Valley Gardens Phase 3.
Financial impact
No specific budget or contract amount is stated.
Ward affected
city-wide

Stakeholders named

parsed
Local residents and businessesPublic transport operators and passengersCyclists and active travel usersPedestriansDisabled and vulnerable peopleTaxi operatorsEmergency servicesHeritage and conservation organisationsTourism and hospitality businessesEvent organisersLocal traders and community groups

Next steps

parsed
  • Continue Valley Gardens Member Working Group meetings to inform final matters such as material selection for hard and soft landscaping.
  • Present final material selections and construction drawings to the Valley Gardens Member Working Group.
  • Consult conservation stakeholders on the detailed public space and War Memorial designs.
  • Build maintenance into the construction contract for the three-year monitoring period.
  • Monitor air quality for three years after construction is completed.
  • Undertake further feasibility and design work for items including the Art Deco bus shelter reuse, underground bins and possible accessible toilet.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage