Decision - Moulsecoomb Hub & Housing Project Update

Brighton and Hove Policy & Resources Committee Decided 29 Jul 2022 for determination GET /api/coverage
Decision maker
Policy & Resources Committee
Report author
Stephen Marsden
Published
29 Jul 2022
Reference
6683

As published

the council's own words, unedited

RESOLVED: That Housing Committee: 2.1 Recommends to Policy & Resources committee that Policy & Resources Committee: 2.1.1. Notes the progress made on the Moulsecoomb Hub and Housing project to date 2.1.2. Authorises officers to progress RIBA stage 4 (technical design) 2.1.3. Approves an additional budget of £3.771m for this work, to be funded by HRA Borrowing and BLRF grant allocation and included as part of the 2022/23 HRA Capital Programme 2.1.4. Approves the grant-funded enabling works to commence, including the demolition of Moulsecoomb Hubs north and south, to be financed by £1.694m BLRF grant allocation 2.1.5. Confirms minor changes to the appropriation of land as approved at Policy & Resources Committee in November 2021 to include land around the buildings on site, and delegates authority to the Executive Director of Housing, Neighbourhood & Communities to approve further minor changes That Policy & Resources Committee: 2.1.6. Notes the progress made on the Moulsecoomb Hub and Housing project to date. 2.1.7. Authorises officers to progress RIBA stage 4 (technical design) 2.1.8. Approves an additional budget of £3.771m for this work, to be funded by HRA Borrowing and BLRF grant allocation and included as part of the 2022/23 HRA Capital Programme 2.1.9. Approves the grant-funded enabling works to commence, including the demolition of Moulsecoomb Hubs north and south, to be financed by £1.694m BLRF grant allocation 2.1.10. Confirms minor changes to the appropriation of land as approved at Policy & Resources Committee in November 2021 to include land around the buildings on site, and delegates authority to the Executive Director of Housing, Neighbourhood & Communities to approve further minor changes.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 5333/1413 tokens · 10693ms · parsed 9 Sep 2026 11:38
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The report provided an update on the Moulsecoomb Neighbourhood Hub and Housing Project and sought approval to proceed with technical design and grant-funded site-enabling works. The project is intended to deliver 212 affordable homes, a new civic hub and improved public spaces, while further cost certainty is obtained before seeking approval for the full construction budget.

Recommendation
To note progress, authorise RIBA Stage 4 technical design, approve an additional £3.771 million budget funded by HRA borrowing and Brownfield Land Release Fund grant allocation, approve £1.694 million of grant-funded enabling works including demolition of Moulsecoomb Hubs north and south, and confirm minor changes to the appropriation of land with delegated authority for further minor amendments.
Financial impact
Additional budget of £3.771 million, comprising £2.077 million new HRA borrowing and £1.694 million Brownfield Land Release Fund grant allocation. The total estimated cost of the RIBA Stage 4 design, site-enabling works and on-costs is £4.083 million.
Ward affected
Moulsecoomb and Bevendean
Decision maker
Policy & Resources Committee
Date in document
29 Jul 2022

Stakeholders named

parsed
Moulsecoomb and Bevendean residentslocal residents and community groupscommunity stakeholder groupfuture residents of the 212 affordable homespeople with disabilities and less ambulant residentsBrighton & Hove City CouncilHomes England

Next steps

parsed
  • Progress RIBA Stage 4 technical design.
  • Commence grant-funded enabling works, including demolition of Moulsecoomb Hubs north and south, infrastructure works, asbestos removal and site clearance.
  • Formalise the revised appropriation of land between the HRA and General Fund.
  • Continue community engagement and develop a revised communications strategy.
  • Negotiate an Agreed Maximum Price at the conclusion of RIBA Stage 4 if the project proceeds through the Council’s Strategic Partnership.
  • Submit a further report in November 2022 seeking the full construction budget and financial appraisal.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.