Decision - Moulsecoomb Hub & Housing Project Update
As published
the council's own words, uneditedRESOLVED: That Housing Committee: 2.1 Recommends to Policy & Resources committee that Policy & Resources Committee: 2.1.1. Notes the progress made on the Moulsecoomb Hub and Housing project to date 2.1.2. Authorises officers to progress RIBA stage 4 (technical design) 2.1.3. Approves an additional budget of £3.771m for this work, to be funded by HRA Borrowing and BLRF grant allocation and included as part of the 2022/23 HRA Capital Programme 2.1.4. Approves the grant-funded enabling works to commence, including the demolition of Moulsecoomb Hubs north and south, to be financed by £1.694m BLRF grant allocation 2.1.5. Confirms minor changes to the appropriation of land as approved at Policy & Resources Committee in November 2021 to include land around the buildings on site, and delegates authority to the Executive Director of Housing, Neighbourhood & Communities to approve further minor changes That Policy & Resources Committee: 2.1.6. Notes the progress made on the Moulsecoomb Hub and Housing project to date. 2.1.7. Authorises officers to progress RIBA stage 4 (technical design) 2.1.8. Approves an additional budget of £3.771m for this work, to be funded by HRA Borrowing and BLRF grant allocation and included as part of the 2022/23 HRA Capital Programme 2.1.9. Approves the grant-funded enabling works to commence, including the demolition of Moulsecoomb Hubs north and south, to be financed by £1.694m BLRF grant allocation 2.1.10. Confirms minor changes to the appropriation of land as approved at Policy & Resources Committee in November 2021 to include land around the buildings on site, and delegates authority to the Executive Director of Housing, Neighbourhood & Communities to approve further minor changes.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 5333/1413 tokens · 10693ms · parsed 9 Sep 2026 11:38The report provided an update on the Moulsecoomb Neighbourhood Hub and Housing Project and sought approval to proceed with technical design and grant-funded site-enabling works. The project is intended to deliver 212 affordable homes, a new civic hub and improved public spaces, while further cost certainty is obtained before seeking approval for the full construction budget.
Stakeholders named
parsedNext steps
parsed- Progress RIBA Stage 4 technical design.
- Commence grant-funded enabling works, including demolition of Moulsecoomb Hubs north and south, infrastructure works, asbestos removal and site clearance.
- Formalise the revised appropriation of land between the HRA and General Fund.
- Continue community engagement and develop a revised communications strategy.
- Negotiate an Agreed Maximum Price at the conclusion of RIBA Stage 4 if the project proceeds through the Council’s Strategic Partnership.
- Submit a further report in November 2022 seeking the full construction budget and financial appraisal.