Decision - New Homes for Neighbourhoods Rotherfield Crescent - Procurement of Contractor

Brighton and Hove Policy & Resources Committee Decided 1 Dec 2022 approved GET /api/coverage
Decision maker
Policy & Resources Committee
Report author
—
Published
1 Dec 2022
Reference
6800

As published

the council's own words, unedited

RESOLVED : That the Committee – (i) Approved the increase of £ 0.600m in the Design Competition budget allowance to deliver the Rotherfield Crescent scheme for three, three-bedroom homes based on the Pre-Tender Estimate £ 1.192m ; (ii) Delegated authority to the Executive Director for Housing, Neighbourhoods and Communities to procure and award a contract for construction via an existing Framework (the preferred route) or other compliant route .

Parsed from the document

gpt-5.6-luna-2026-07-09 · 8378/1893 tokens · 13005ms · parsed 9 Sep 2026 11:53
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The report sought approval for a value-engineered scheme to demolish the existing council garages at Rotherfield Crescent and build four new council homes. Members were asked to approve Option 1, procure a development partner and professional services, set rents at 37.5% of Living Wage, and approve land appropriation arrangements.

Recommendation
Note the options and associated risks; agree Option 1 and approve the proposed scheme of four new council homes, procurement of a development partner and professional services with delegated authority to award the contract, and rent levels at 37.5% of Living Wage. Recommend that Policy, Resources & Growth Committee appropriate the former garages site for planning purposes and delegate authority for its later appropriation for housing once development is complete.
Financial impact
Total estimated scheme costs of £1.037 million, including construction works, contingency, inflation and professional fees. Thirty percent of the cost can be funded from retained Right to Buy receipts; the 37.5% Living Wage rent option is modelled to produce a surplus of £0.103 million over a 60-year period.
Ward affected
Patcham
Decision maker
Housing and New Homes Committee, with recommendation to Policy, Resources & Growth Committee
Date in document
19 Sep 2018

Stakeholders named

parsed
Brighton & Hove City CouncilResidents and garage owners at Rotherfield CrescentApplicants from the Homemove registerInnes AssociatesMillbridge GroupPotter RaperPolicy, Resources & Growth Committee

Next steps

parsed
  • Procure a development partner and professional services in accordance with the council’s procurement requirements.
  • Grant delegated authority to the Executive Director, Environment, Economy and Culture, in consultation with the Executive Director, Finance and Resources, to award the contract after procurement.
  • Innes Associates to hold a public exhibition and make final design adjustments.
  • Submit a planning application, anticipated in Autumn 2018.
  • Appropriate the former garages site for planning purposes if approved by Policy, Resources & Growth Committee.
  • Appropriate the developed site for housing through an Appropriation Memo once development is complete.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage