the council's own words, uneditedReport asking for agreement to procure support for creating a Development Brief for the future development of the Black Rock site.
RESOLVED : That the Committee – (i) Agreed the proposals and timetable for producing a Development Brief for the future development of the Black Rock site as outlined in para 3.30-3.42; (ii) Agreed that £100,000 of capital funding is allocated to procure professional support for the production of the Brief associated surveys and investigations; (iii) Agreed to the use of the site for meanwhile uses and entertainment space as detailed in para 3.10-3.23, and that the meanwhile uses and lettings policies take into account the need to prioritise local businesses and foster a local circular economy.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 6753/1537 tokens · 12907ms · parsed 9 Sep 2026 11:48The committee agreed proposals and a timetable for producing a Development Brief for the future development of the Black Rock site. It also agreed to allocate £100,000 for professional support and to use the site for temporary events and entertainment from July 2023 to July 2025.
Stakeholders named
parsedNext steps
parsed- Procure professional support for the Development Brief, associated surveys and investigations.
- Develop and consult on the Development Brief during 2023.
- Invite expressions of interest and market the development opportunity.
- Evaluate bids and appoint a development partner by February 2025.
- Use Black Rock as a temporary open-air event and entertainment space from July 2023 to July 2025.