Decision - Response to Notice of Motion- Victoria Fountain

Brighton and Hove Environment, Transport & Sustainability Committee Decided 15 Nov 2022 approved GET /api/coverage
Decision maker
Environment, Transport & Sustainability Committee
Report author
Angela Dymott
Published
17 Nov 2022
Reference
6766

As published

the council's own words, unedited

That Committee notes : 1) The update on the Victoria Fountain structural repair and refurbishment project to bring the asset back into a good condition and working order. 2) The findings of the HOP Victoria Gardens Old Steine, Assessment of Shallow Geological Anomalies Report.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 2873/719 tokens · 5639ms · parsed 9 Sep 2026 11:54
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The committee received an update on the structural repair and refurbishment of the Victoria Fountain and the investigation into a swallow hole at Victoria Gardens Old Steine. Hemsley Orrell Partnership found that the hole was likely caused by water flow and surface loading, and recommended a system to assess heavy loads before machinery is used.

Recommendation
That the Committee notes the update on the Victoria Fountain structural repair and refurbishment project and the findings of Hemsley Orrell Partnership’s Victoria Gardens Old Steine, Assessment of Shallow Geological Anomalies report.
Financial impact
£250,000 has been included in the Capital Investment Programme for 2022/23 for the Victoria Fountain repairs, funded through capital borrowing; additional costs may require a review of the Planned Maintenance Budget.
Ward affected
Regency
Decision maker
Environment, Transport and Sustainability Committee
Date in document
15 Nov 2022

Stakeholders named

parsed
Brighton & Hove City CouncilHemsley Orrell Partnershiplocal residentsspecialist contractorsthe successful refurbishment contractor

Next steps

parsed
  • Analyse the two tender returns received for the refurbishment works.
  • Appoint the successful contractor in late November 2022, subject to confirmation of costs and funding.
  • Aim to start work on site in mid-December 2022 and complete the refurbishment by the end of March.
  • Use the heavy-load check system developed by Hemsley Orrell Partnership to mitigate the risk of further geological anomalies.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage