Decision - Eastergate Road Former Garage Site Redevelopment
As published
the council's own words, uneditedApproval of Scheme and Procurement of Main Contractor
RESOLVED: 2.1 That Housing Committee: 2.1.1 Approves the recommendation of the Procurement Advisory Board (PAB) on 17 October 2022 that the main contractor is procured by Direct Award from an appropriate public sector procurement Framework, or by restricted tender. 2.1.2 Delegates authority to the Executive Director for Housing, Neighbourhoods & Communities to take all steps necessary to procure and award contract(s) for design work to the end of RIBA Stage 4 (Technical Design), this to include construction works (commitment to progress works will be dependent on further budget approval) at the former garage site, Eastergate Road. 2.2 That Policy & Resources Committee: 2.2.1 Approves a budget for the former garage site at Eastergate Road of £293,000 to allow the completion of design work to the end of RIBA Stage 4 (technical design), and for site clearance works, financed by a mixture of HRA borrowing and Brownfield Land Release Fund (BLRF) grant.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 4751/1502 tokens · 10058ms · parsed 9 Sep 2026 11:39The report proposed progressing the former Eastergate Road garage site to the end of the pre-construction phase, including design work to RIBA Stage 4 and site clearance. The scheme is intended to provide up to 30 move-on homes for young people with low-level support needs, with YMCA DLG intended to manage the completed scheme.
Stakeholders named
parsedNext steps
parsed- Procure the main contractor by direct award from an appropriate public sector procurement framework or by restricted tender.
- Procure and award contracts for design work through RIBA Stage 4 and associated construction works, subject to further budget approval.
- Carry out site clearance works.
- Continue discussions with YMCA DLG on lease Heads of Terms and confirm the service provider.
- Return to committees in June 2023 for approval of the final construction-phase budget.
- Continue consultation with ward councillors, lead members, local residents, commercial neighbours and community groups.