Decision - Hollingdean Depot Office Accommodation Project
As published
the council's own words, uneditedRESOLVED : That the Committee – (i) Agreed to the removal of the old operations building and associated structures and replace with a new two-story office block to accommodate the teams at the Hollingdean Depot, currently in portacabins. (ii) Agreed to transfer the £ 1.000m capital budget previously allocated for the Hollingdean Depot Site Surface works to fund the additional costs for the works in recommendation 2.1 and for this sum be incorporated into the Council's Capital Investment Programme for 2023/24. (iii) Granted delegated authority to the Executive Director Economy, Environment & Culture to take all steps necessary to progress with the Hollingdean Depot Accommodation Project.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 6330/998 tokens · 8430ms · parsed 9 Sep 2026 11:56The business case recommends replacing the existing Hollingdean Depot office accommodation with a modular building, after asbestos was detected and the current portacabins were found to be unsuitable. The preferred option is estimated to cost £2.95 million, requiring approximately £950,000 of additional funding beyond the £2 million already allocated.
Stakeholders named
parsedNext steps
parsed- Complete and review the feasibility study.
- Secure additional funding through corporate borrowing approved by Policy and Resources Committee or unsupported borrowing funded from service budgets.
- Relocate the comms room and complete the associated re-cabling and IT fit-out.
- Procure demolition separately from the modular building contract.
- Tender the modular building through an approved framework and appoint a main contractor.
- Submit a planning application and confirm compliance with building regulations.
- Complete the Equalities Impact Assessment and Data Privacy Impact Assessment.
- Complete the project by Spring 2024 and move staff into the new building during Summer 2024.