Decision - A259 Active Travel Improvement Scheme Fourth Avenue - Wharf Road

Brighton and Hove Transport & Sustainability Committee Decided 21 Jun 2023 approved GET /api/coverage
Decision maker
Transport & Sustainability Committee
Report author
Tracy Beverley
Published
23 Jun 2023
Reference
6960

As published

the council's own words, unedited

This is a special report following the administrations requirements for the scheme. The report makes recommendations to enable officers to meet the requirements of the administration.

1) That the Committee agrees to redesign the A259 Fourth Avenue to Wharf Road scheme. 2) That the Committee notes that significant additional funding will be required to redesign and deliver the final scheme. The final scheme design and funding requirements will be subject to a further report to this committee, including funding sources such as other external grant or reallocation of the Councils Programme. 3) That Committee delegates authority to the Executive Director, Economy, Environment & Culture to take all steps necessary to terminate the current call-off Contract for the A259 Fourth Avenue to Wharf Road Active Travel Scheme and notes the financial implications of both the stand-down charges and termination fees as detailed in section 7 of this report.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 4056/1574 tokens · 11905ms · parsed 9 Sep 2026 12:00
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The report proposed redesigning the A259 Fourth Avenue to Wharf Road active travel scheme to provide a continuous bi-directional cycle lane, improve pedestrian facilities and retain vehicle lanes where possible. It also proposed terminating the existing works contract to avoid ongoing stand-down charges, with a further report required on the redesigned scheme and additional funding.

Recommendation
Agree either recommendations 2.1 to 2.3: redesign the scheme, note that significant additional funding will be required, and delegate authority to the Executive Director, Economy, Environment & Culture to terminate the current call-off contract; or agree recommendation 2.4 that the works approved in March 2022 continue.
Financial impact
The current call-off contract is £739,000 and the estimated final scheme value is £940,000. Stand-down charges are estimated at £18,747 per week, redesign internal resources are estimated at £72,000, and additional capital funding will be required.
Ward affected
city-wide
Decision maker
Special Transport & Sustainability Committee
Date in document
21 Jun 2023

Stakeholders named

parsed
pedestrianscyclistslocal residentsbusinessesdisability interest groupsActive Travel EnglandDepartment for TransportWest Sussex County CouncilR.J. Dance

Next steps

parsed
  • Redesign the A259 Fourth Avenue to Wharf Road scheme over approximately six months.
  • Terminate the current call-off contract if the redesign option is agreed, with termination amounts calculated under the contract terms.
  • Prepare a further report on the final scheme design, detailed costs and funding sources.
  • Communicate the revised timeframe and programme impact to Active Travel England.
  • Update the Equalities Impact Assessment and undertake further consultation if significant design changes are proposed.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this