Decision - Kingsway to the Sea

Brighton and Hove Strategy, Finance & City Regeneration Committee Decided 22 Jun 2023 approved GET /api/coverage
Decision maker
Strategy, Finance & City Regeneration Committee
Report author
Toni Manuel
Published
23 Jun 2023
Reference
6955

As published

the council's own words, unedited

Update on the status of the project to transform the land from the west of the King Alfred Leisure Centre to the easterly section of Hove Lagoon.

RESOLVED: That the Committee: 2.1 Approves the reduction in scope of the project to fit within the total budget outlined in paragraph 3.8 below and delegates authority to the Executive Director for Economy, Environment & Culture to take all steps necessary to re-commence the project. 2.2 Agrees that the total project budget has increased to £13.76m as set out in paragraph 3.8 below. Also agrees that there is a further opportunity to return to this committee in July 2023 if additional funding becomes available to deliver an increased scope. 2.3 Agrees that paragraph 3.13 is an indicative schedule of omissions from the project and that some items may be changed or substituted to reach the target budget figure. 2.4 Notes the target completion of the Levelling Up Fund spend by the 31 st March 2024. 2.5 Notes that receipt of next and future payments from the Levelling up Fund is subject to their acceptance of a change request detailing the proposed omissions. A further report may be required to this Committee depending on the view from Government.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 5070/1558 tokens · 11000ms · parsed 9 Sep 2026 12:01
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The committee considered cost increases that created a funding gap for the Kingsway to the Sea project. It approved a reduced project scope within a total budget of £13.76m and authorised the Executive Director for Economy, Environment & Culture to take the steps needed to restart the project, subject to approval from the Levelling Up Fund.

Outcome
approved
Recommendation
Approve a reduced scope to fit within the total budget, increase the total project budget to £13.76m, delegate authority to the Executive Director for Economy, Environment & Culture to recommence the project, and note the Levelling Up Fund spending deadline and requirement for a change request.
Financial impact
The total project budget increased to £13.761m, including a £12.7m construction budget. The project had £1.666m spent to date and a potential further funding gap of £2.22m to retain additional facilities.
Ward affected
Wish, Westbourne and Poets Corner
Decision maker
Strategy, Finance & City Regeneration (SFCR) Committee
Date in document
22 Jun 2023

Stakeholders named

parsed
West Hove Seafront Action GroupHove and Kingsway Bowling ClubFriends of Hove LagoonKing Alfred Tennis ClubHove Beach Croquet Clubsand and wheeled sports representativeslocal businessesGovernment’s Levelling Up Fund departmentBrighton & Hove City Council

Next steps

parsed
  • Submit a change request to the Government’s Levelling Up Fund department detailing the reduced scope and requesting acceptance of the changes and any extension to the spending deadline.
  • Agree a price with the contractor for the reduced scheme.
  • Recommence construction, starting with the Outdoor Sports Hub, once Government funder approval is received.
  • Continue design and value-engineering work to finalise the omissions and achieve the target budget.
  • Continue consultation with the West Hove Seafront Action Group and other stakeholders.
  • Consider returning to the committee in July 2023 if additional funding becomes available.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage