Decision - Housing Major Capital Works Framework review of procurement options

Brighton and Hove Housing & New Homes Committee Decided 20 Sep 2023 for determination GET /api/coverage
Decision maker
Housing & New Homes Committee
Report author
Martin Reid
Published
21 Sep 2023
Reference
7024

As published

the council's own words, unedited

This report seeks approval for the dissolution of the existing Housing major capital works framework arrangement for Lot 2, works over £300,000, due to our being unable to secure sufficient tenders from the contractors currently on the framework. The report recommends replacement of this element of the framework with the procurement of a compliant alternative framework and /or formation of a suitable list of approved contractors for each project to ensure that we receive sufficient tender bids for assurance of value for money and cost comparison.

RESOLVED: 2.1 That Committee delegates authority to the Executive Director Housing, Neighbourhoods & Communities to procure a Framework Agreement for major works over £300,000 and to enter into call-off contracts for works under that Framework Agreement. 2.2 That Committee grants delegated authority to the Executive Director Housing, Neighbourhoods & Communities to procure and award contracts for major works over £300,000 using other routes to market where the use of a Framework Agreement is not available or appropriate.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 3668/863 tokens · 6812ms · parsed 9 Sep 2026 12:01
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The report proposes replacing the current Lot 2 major works framework because only two of its six contractors are submitting tenders, reducing competition for works over £300,000. It seeks delegated authority to procure a replacement framework or use other compliant procurement routes to increase contractor capacity and improve value for money.

Recommendation
Delegate authority to the Executive Director Housing, Neighbourhoods & Communities to procure a Framework Agreement for major works over £300,000 and enter into call-off contracts, and to procure and award major works contracts over £300,000 using other routes to market where a framework is unavailable or inappropriate.
Financial impact
The 2023/24 capital programme includes an approximate budget of £8,000,000 for major works; the recommendations do not affect the approved 2023/24 budget.
Ward affected
city-wide
Decision maker
Housing & New Homes Committee
Date in document
20 Sep 2023

Stakeholders named

parsed
Council tenantsLeaseholdersResidentsMajor works contractorsHousing Investment & Asset Management serviceCorporate Procurement

Next steps

parsed
  • Procure a framework agreement for major works over £300,000.
  • Use other compliant routes to market where a framework is unavailable or inappropriate.
  • Enter into call-off or project-specific contracts subject to budget approval.
  • Include a plan for delivering major projects over the next five years in the 2024/25 budget paper.
  • Continue consulting residents on major works projects.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage