Decision - Greater Brighton Hydrogen Strategy
Brighton and Hove
Greater Brighton Economic Board
Decided 7 Feb 2023
approved
GET /api/coverage
Decision maker
Greater Brighton Economic Board
Report author
Kirsten Firth
Published
25 Jul 2023
Reference
6989
As published
the council's own words, unedited
Outlines the key points of a Hydrogen Strategy for the Greater Brighton and wider Sussex area, including potential development, locations, economic growth.
1) That the Board notes the findings of the Greater Brighton Hydrogen Strategy (Appendix 1) and agrees that this should form the basis of future work on hydrogen in the city region. 2) That Board agrees to receive a future report outlining proposals for Hydrogen Sussex to become a self-sustaining organisation.
Everything below was read out of a PDF by a model
It is useful and it is not authoritative. The document it came from is linked in the
rail, and where the two disagree the document is right.
The report presented the Greater Brighton Hydrogen Strategy and asked the Greater Brighton Economic Board to endorse its findings and action plan as the basis for future hydrogen-related work across the city region. It also proposed further consideration of options for Hydrogen Sussex to become a self-sustaining organisation.
Recommendation
That the Board note the findings of the Greater Brighton Hydrogen Strategy and agree that it should form the basis of future work on hydrogen in the city region, and that the Board receive a future report outlining proposals for Hydrogen Sussex to become a self-sustaining organisation.
Financial impact
The Greater Brighton Economic Board provided £25,000 towards the cost of the Greater Brighton Hydrogen Strategy. Additional funding was secured from Coast to Capital LEP’s Regional Projects Business Case Development Fund; no further contributions are required at this point.
Ward affected
city-wide
Decision maker
Greater Brighton Economic Board
Date in document
7 Feb 2023
Stakeholders named
parsed
Hydrogen Sussexbusinessespublic bodiesuniversitiesutilitieslocal authoritiesregional organisationsthe wider community
Next steps
parsed
Use the Greater Brighton Hydrogen Strategy as the basis for future work on hydrogen in the city region.
Bring a future report to the Board outlining proposals for Hydrogen Sussex to become a self-sustaining organisation.
Bring any further requests for financial support back to the Board.
Precedents
not built
"Decided elsewhere" is not built
Finding the same decision in other councils needs semantic matching over decision
text, which is part of the search rewrite. Until then, the council's own decisions
list is the way through.