Decision - Greater Brighton Retrofit Taskforce

Brighton and Hove Greater Brighton Economic Board Decided 18 Oct 2022 approved GET /api/coverage
Decision maker
Greater Brighton Economic Board
Report author
Andy Hill
Published
25 Jul 2023
Reference
6985

As published

the council's own words, unedited

1) That the Board notes the research has proven the original concept that Council budgets taken together with Government and Supply Chain collaboration is the optimal way to deliver a medium to long term plan for zero carbon council homes, and that there is a trade-off between carbon, capital spend, and cost to occupier. 2) That the Board given the context of the cost-of-living crisis agrees that a programme to target fuel costs at the same time as developing the supply chain forms the early part of a programme roll out. 3) To Board agrees to further develop the zero-carbon business case with a view to submit a joint proposal to Government/BEIS to trial an approach in the Sussex area. 4) That the Board agrees with the aim to submit a joint bid for grants to trial the collaborative working of the Board. This will lay the foundation and provide the potential for rapid future expansion. The bid will be an aggregated pipeline with individual authority control. 5) That the Board agrees to explore the best procurement option for delivering the zero-carbon works, and notes that Clear Futures (a joint venture between Lewes and Eastbourne Councils, AECOM and Robertson Construction) could be one such option to consider.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 3403/1631 tokens · 10383ms · parsed 9 Sep 2026 12:03
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The Greater Brighton Economic Board considered emerging conclusions from the Retrofit Task Force on achieving zero-carbon council homes by 2030. It supported developing a programme focused initially on reducing fuel costs, preparing a joint proposal and grant bid, and exploring procurement options for zero-carbon works.

Outcome
approved
Recommendation
The Board was recommended to note the research findings; develop an early programme targeting fuel costs and supply-chain capacity; further develop a zero-carbon business case and joint proposal to Government/BEIS; submit a joint grant bid; and explore procurement options, including Clear Futures.
Financial impact
The full scope of the cost of the works has yet to be quantified; future retrofit works are expected to use existing Housing Revenue Account (HRA) budgets, supplemented by grants where available.
Ward affected
city-wide
Decision maker
Greater Brighton Economic Board
Date in document
18 Oct 2022

Stakeholders named

parsed
Greater Brighton Economic BoardGreater Brighton councilsCouncil and social housing residentsPrivate housing residentsGovernment/BEISHousing Revenue Account budget holdersSkills colleges and apprenticesRetrofit supply chain

Next steps

parsed
  • Further develop the zero-carbon business case.
  • Prepare a joint proposal to Government/BEIS to trial an approach in Sussex.
  • Explore and submit a joint grant bid for collaborative working.
  • Explore the best procurement option for delivering zero-carbon works.
  • Lewes District Council will report back to the Board in April 2023.
  • Provide the Board with an interim summary report of the Taskforce work.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage