the council's own words, uneditedThis report presents the 2025-26 in-year financial performance to Month 7 (October) for noting by Cabinet and seeks approval for any capital variations, reprofiling, exception measures or new reserves.
1) Cabinet notes the forecast risk position for the General Fund, which indicates a potential forecast overspend risk of £7.776m. 2) Cabinet notes the forecast overspend risk for the separate Housing Revenue Account (HRA), which is an overspend of £1.216m. 3) Cabinet notes the forecast overspend risk for the ring-fenced Dedicated Schools Grant, which is an overspend of £2.463m. 4) Cabinet notes the forecast position on the Capital Programme which is an underspend variance of £10.963m. 5) Cabinet approves the capital budget variations and re-profiling requests set out in Appendix 6. 6) Cabinet approves the new capital schemes requested in Appendix 7. 7) Cabinet notes the Treasury Management mid-year review as set out in Appendix 8 and summarised in paragraph 9.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 6045/1305 tokens · 13125ms · parsed 8 Sep 2026 11:39The report provides a Month 7 update on capital budgets, forecast outturns, variations, slippages and reprofiling across families and children, adult social care, city operations, central services and the Housing Revenue Account. Most non-HRA budgets are forecast to be on budget, while the HRA is forecast to underspend by £10.921 million, mainly because of delays to housing investment and building safety-related works.
Stakeholders named
parsedNext steps
parsed- Continue monitoring delivery of capital schemes and reprofiling budgets into future financial years where required.
- Review and authorise major housing capital works in line with Building Safety Regulations requirements.
- Develop programmes and procurement arrangements for service risers and asbestos removal works.
- Keep the windows programme under review and report any scope to increase spend at TBM09.
- Explore options to repurpose potential savings from delayed public conveniences works, subject to decisions on savings proposals.