Decision - Safer, Better Streets: 2024/2025 Programme

Brighton and Hove Transport & Sustainability Committee Decided 5 Dec 2023 approved GET /api/coverage
Decision maker
Transport & Sustainability Committee
Report author
Jazmine Hayes
Published
19 Dec 2023
Reference
7089

As published

the council's own words, unedited

A report presenting the proposed 2024/2025 Safer, Better Streets programme priority list, a summary of on-going and planned works associated with the Safer, Better Streets programme and an update on the programme process

1) That Committee notes the new SBS Priority List, included in Appendix 1, produced in line with the approved SBS assessment methodology. 2) That Committee grants approval for officers to progress design and construction work on the identified locations in the SBS Priority List 'Top Twelve Priority list' identified at Table 2 in this report, subject to funding, consultation and any required Traffic Regulation Orders (TROs) processes. 3) That Committee notes the changes to the SBS assessment process and agrees the amended process in Appendix 2, to be used for future assessments.

Parsed from the document

gpt-5.6-luna-2026-07-09 · 3120/984 tokens · 8215ms · parsed 9 Sep 2026 12:07
Everything below was read out of a PDF by a model It is useful and it is not authoritative. The document it came from is linked in the rail, and where the two disagree the document is right.

The report provides an update on Safer, Better Streets projects delivered, underway or planned across the city. It covers pedestrian crossings, high-risk collision sites, developer-funded works, signalised crossing upgrades and improvements funded through the Safer Roads Fund.

Recommendation
No specific recommendation is stated in the document; it provides a progress update on associated Safer, Better Streets projects.
Financial impact
No specific financial amount is stated.
Ward affected
city-wide
Decision maker
T&S Committee
Date in document
5 Dec 2023

Stakeholders named

parsed
pedestrianscyclistslocal communitiesward membersmotorised vehicle users

Next steps

parsed
  • Continue or commence construction and design works at the listed sites according to the expected delivery timetable.
  • Progress the Whitehawk Road, Roedean Road, Bristol Gardens and Arundel Road scheme towards construction in early 2024 following the traffic regulation order process.
  • Continue developing improvements along the A2010 corridor, including Russell Road/West Street and West Street/North Street.
  • Engage ward members and the local community on options for Fox Way.
  • Complete design and road safety audit work for the Withdean Stadium crossing before construction.
  • Pause the A293 Roundabout South Arm scheme until future funding can be allocated.

Precedents

not built
"Decided elsewhere" is not built Finding the same decision in other councils needs semantic matching over decision text, which is part of the search rewrite. Until then, the council's own decisions list is the way through.
Documents
Who voted
Not extracted
Recorded votes are published in the minutes but we do not yet parse them into a direction per councillor. This page will not guess at one.
Watch this
Not built
Following a decision would ask you for a channel — email or webhook — at the point of following, with no default. Neither channel exists yet.
GET /api/coverage