Decision - Sports Facilities Investment Plan - Progress Update
As published
the council's own words, uneditedA progress update on the delivery of the SFIP - including next steps for the King Alfred redevelopment project and other capital projects.
RESOLVED: That Committee: 1. Noted the progress and timeline for implementing the capital projects at Withdean Sports Complex which will further enhance the North Hub, as outlined in the Sports Facilities Investment Plan. 2. Noted the progress on the King Alfred/West Hub redevelopment project and supports the upcoming engagement and consultation on site options planned for early 2024.
Parsed from the document
gpt-5.6-luna-2026-07-09 · 6337/1287 tokens · 9115ms · parsed 9 Sep 2026 12:07The committee was asked to note progress on sports-facility investment, particularly the three projects planned at Withdean Sports Complex to strengthen the North Hub. It was also asked to support engagement and consultation on location options for the replacement King Alfred Leisure Centre and West Hub redevelopment in early 2024.
Stakeholders named
parsedNext steps
parsed- Continue the Withdean Sports Complex capital projects, with completion anticipated in Spring 2024.
- Continue work with Continuum Sport and Leisure to assess West Hub delivery proposals and identify a preferred option supported by a business case.
- Undertake online and face-to-face engagement on West Hub site options in early 2024, with the process expected to finish by the end of March 2024.
- Appoint a lead architect and begin concept design in summer 2024.
- Begin the planning application process in mid-to-late 2024.
- Procure the main design and build contractor in 2025.
- Begin initial works on site in late 2025 or 2026, with completion of the new facility planned for 2028.